An alternate study to meet the LCA Mk.1A/Mk2 requirement. One of the great lacunae in planning of our weapons programmes is the lack of alternative studies. Even in tightly state controlled economies competitive proposals are mandatory. It is economical in every sense to have competition.
The LCA Mk1a /Mk2 are engineering effort wise new proposals. The prototypes are expected circa 2025. We have no back ups for this class of aircraft. The Bisons will have gone.
It seems that the fuselage of the MiG 27 combined with a new fixed wing - a 45 degree based on the existing wing or one based on the LCA's wing plus a tail could be copied much faster.and could meet all the problems- lack of real estate, gun firing,etc reported in the CAG report.
At least a preliminary study is mandatory! It should cost no more than a crore and six months.
The LCA Mk1a /Mk2 are engineering effort wise new proposals. The prototypes are expected circa 2025. We have no back ups for this class of aircraft. The Bisons will have gone.
It seems that the fuselage of the MiG 27 combined with a new fixed wing - a 45 degree based on the existing wing or one based on the LCA's wing plus a tail could be copied much faster.and could meet all the problems- lack of real estate, gun firing,etc reported in the CAG report.
At least a preliminary study is mandatory! It should cost no more than a crore and six months.
A proposal to study
the MiG23/27 air frame with the GE F414 engine
As a backup for
the LCA Mk1A and the Mk 2 programmes.
Prodyut Kumar
Das
Designer/
Engineer
Professor IITK etc. (retd.) Kolkata,
27 February 2019
TABLE OF
CONTENTS pp.
1.
SYNOPSIS 3
2.
THE NEED FOR THE
STUDY 4
3.
THE ADVANTAGES
OF USING A BASE A/C 4
4.
THE MIG 23/27 AS
A BASE 4
5.
BACKGROUND
TECH.NOTES MIG 23/27 5
6.
THE DEVELOPMENT
STRATEGY 6
7.
THE ENGINEERING
CHANGES 6
8.
THE LIMITS OF
THE STUDY 8
9.
OTHER PROJECT
STUDIES 9
10. ESTIMATED MANPOWER 9
11. CONCLUSIONS 10
12. A TABLE OF COMPARISONS 10
13. SIDE VIEWS 11
SYNOPSIS
The
IAF is today in a critical situation in relation to the LCA category of aircraft.
This has happened because of past lacunae in organization and management of the
LCA programme. We have to consider what would have been our situation today had
we in 1989 when the review had shown that the proposed LCA was not going to meet
specifications, we had alternative projects studies to fall back on.
What the impact of such precautions may have had on the situation today needs
no elaboration
The LCA Mk1 does not meet specifications. The
PAC 2153/ CAG report 114 indicate that the airframe is deficient in performance
and expandability. The extent of re-engineering on the airframe is around 40% for the airframe alone. The
configuration is difficult to develop. The amount of work to transform the Mk1 to
the Mk.1A is at least as much as was required to transform the Mirage III into
the Mirage 2000. The seasoned, well organized French took four years to get the
Mirage 2000 into IOC.
The
Mk2 is almost a new aircraft with attendant risks. India must have viable
alternatives rather than rely on “Hope” when 2023 comes. There is a strong need
as of the present for a “what if –in case” study of meeting the
LCA Mk2 specifications based on the proven MiG23/27 along with several similar such studies. Such back up studies are standard practice in most aircraft programmes
and should have been done ab initio at the launch of the LCA programme.
This
proposed project is to study if a structural surgery of the MiG 23/27 series
aircraft.
Structural
surgery is the next evolutionary step to the upgrade programmes carried out on
the Jaguar, MiG 21 and the MiG 23 aircraft and about which the IAF has
commendable experience. In the upgrades
programme the systems have to be upgraded within the constraints of “not
touching the airframe”.
In structural surgery
(see
Indian Defence Review paper II/1990 pp.110-119 by the present author) the airframe is also modified to evolve
a new and more suitable aircraft. The MiG 27 itself is an example of structural
surgery on the basic MiG 23 aircraft with changes to the nose, cockpit,
intakes, wheels and afterburner to make the aircraft suitable for close support
duties. The Israeli Kfir is another example.
Since
modern engines and avionics are more compact, lighter and superior in
performance to those of the MiG 23 vintage the advances in performances seen in
Upgrades are further enhanced and optimized by the structural modification of a
basic airframe. It is possible to evolve a design that will not only meet the
Tejas Mk2 requirements it will be a more certain to achieve its time targets
thanks to a more certain “base” i.e. the MiG 23/27 aircraft. The comparative
figures are on page 10.
A
provisional funding of Rs. 5 crores for the project study and a time scale of 6
to 8 months should be sufficient. If it cannot be done in that time it will
never be done. Te sum of money is affordable but potential in terms of time
saving and “pacing” the LCA project, and the knowledge gained is incalculable.
THE NEED FOR THE
STUDY
The
Tejas programme continues to be uncertain. This is reflected in the recent CAG
report. In summary:
i)
The
airframe is significantly overweight. It so happens that the configuration is
particularly weight sensitive.
ii)
It
will not achieve its range payload specifications.
iii)
The
design still needs considerable refinement and cleaning up. It will not meet
its energy related performance specifications.
iv)
The
airframe is too small to house all the equipment now desired.
The
configuration of the aircraft- tailless delta with FBW results in any change leads
to a cascade of changes. Whilst technically there are no big challenges in
doing all of the above these changes have not happened 18 years after first
flight.
To
base the successor design LCA MK2 on a somewhat “kuchha” base of the LCA Mk.1 as
it exists at present without having a
back up may lead to a repetition of what has happened previously. The strongest
reason is the poor delivery on promises by the concerned organizations which
now has to be planned for.
THE ADVANTAGES
OF USING A BASIS AIRCRAFT
1)
CFD
and wind tunnel studies are useful for comparison but less accurate and
reliable in absolute terms. This is eliminated as the basis aircraft acts as a
full scale wind tunnel model and also can be instrumented to generate needed
data.
2)
Less
experienced design teams may find it difficult to design a service friendly
aircraft. The use of an existing design gives a readymade list of features to
be retained or need to be improved.
3)
Advances
in technology over the design era- sixty years in the case of the MiG 23/27
means significant and guaranteed improvements in utility can be achieved –even
in a “ditto” or “Chinese” copy. The CPAFAF‘s TU-16/H5 is a case to the point.
4)
Very
large efforts required to perfect handling, cockpit ergonomics, safety and
Weapons delivery and gun firing which may require an additional thousand
sorties are reduced to a fraction.
5)
There
are psychological resistances during the certification process. The
availability of proven structures and systems speeds up the process and these
are considerable.
The
intelligent designer can slash the work load by 50 to 70%.
THE MiG23/27 AS
A BASIS FOR THE LCA MK.2 SPECIFICATIONS.
i)
The
MiG 23 was the original BVR fighter. Its airframe performance equals or exceeds
those required LCA Mk.2 specifications.
ii)
The
aircraft was in prolonged IAF service and used in combat. Its advantages and
shortcomings are well known to the customer. The exact areas of improvements
are in sharp focus.
iii)
Much
of the documentation and airframes are available as is the human knowledge of
the operators. This information will cut down the need for repetitive trials in
many significant areas- air brake location on the fuselage or gun firing trials
for example. Detail design problems are under emphasized in India and are more
time consuming than aerodynamic problems and make the difference between a
disliked aircraft and a well loved one.
iv)
“De-tuning” the
design from a Mach 2.3 to Mach 1.6 will easier than refining
the LCA in terms of the speed.
v)
The basic MiG 23/27 airframe is amenable to
development. Being a conventional layout there will be less “cascade” or
“linked” changes. For example if the FBW is not cleared for flight to match the
flight programme the configuration can be be re-arranged as a conventionally
stable aircraft until the problem is sorted out. This is not possible in the
LCA. The proposed canards for the LCA Mk2 will also require considerable
refining lest the traps in the canard
layout-fore plane/main wing interference for example or the higher induced drag
of the low AR fore plane is not fallen into.
vi)
The reduction of the Mach 2.3 speed to Mach 1.6
means that the 72 o wing sweep and indeed the VG requirement can be totally
eliminated. There were Russian proposal to such effect but at that time the
Mach 2.3 top speed was considered sacrosanct so a VG was essential.
THE MiG 23/27:
Some background technical notes.
Why the MiG 23
needed VG.
The
MiG 23/27 was designed in the 1960s and the VVS’s requirements were:
i)
A
top speed of Mach 2.3 at 12,000 mts
ii)
Comprehensive
BVR and IRST capability along with CCM capability.
iii)
Ability
to operate from Soviet Warpac rough fields. The last was not an IAF
requirement.
The
Russians experimented with lift engines and variable geometry (VG) before
choosing the then fashionable VG configuration with outboard hinge and three positions
manually selected swept wing. The heavy weight and the size of the Russian
Saphir 23 radar and the Mach 2.3 top speed needed a heavy and powerful engine
and its consequent load of fuel. This enforced the use of the VG to keep the
landing speed within reasonable limits despite its obvious penalties including around
400kgs extra weight i.e. 4% of the empty weight.
The
reduction in top speed to Mach 1.6 means less required power and hence the size
and weight of the engines. The modern ELTA radar preferred by the customer is
both lighter and requires less base power. 1960s Soviet technology accessories-
hydraulics, electrical and avionics were both heavy and bulky and can be
replaced by lighter modern systems. The same applies for materials including
brake materials. All these result in an inward weight spiral so that the
specifications can be met by a “cut down and squeezed” MiG 23/27 which no
longer requires a VG wing to have an acceptable field performance. The downward
weight spiral estimate is given in the Engineering Changes.
THE DEVELOPMENT
STRATEGY
As
detailed below the direct weight savings
due to replacement of the wing sweep mechanism, the engine and radar will
amount to a weight savings of 1500 kilogrammes. The consequent “cascade”
changes will result in a total weight saving of 2000 kilos.
Since
the top speed of Mach 2.3 is no longer required the max.wing sweep of 72
degrees and the extra engine power will be eliminated and the Mach 1.6 speed of
the specification can be met by a simple fixed wing based on the existing
design but with greater emphasis on leading edge flaps to retain the airfield
performance. No composites will be used
in the prototypes as this militates against the rapid modifications that
are needed
THE ENGINEERING
CHANGES
The
engineering changes vis a vis the Mig 23 will be as listed below.
1.
Radome
The radome contours will be based on the MiG 23
suitably modified for the ELTA 1M 2032. The radome is expected to be somewhat
smaller than the SAPHIR 23 base radome saving weight and drag.
2.
Cockpit
The armoured cockpit of the MiG 27 will be retained.
The Glass cockpit technology already developed for the upgrades will be used. Rear view can be improved via sensor fusion
and MFDs. The ejection seat will be replaced by a modern seat.
3.
Intake
Given the lower power of the GEW 414 or similar
engine vis a vis the R 29B the variable intake of the MiG 23 BN will be
retained as opposed to the fixed intake of the Tejas or the MiG 27 at least in the demonstrator aircraft.
4.
Mid Fuselage
the customer
will have two options:
i)
Keeping
the existing MiG 27 fuselage cross section and use the space for equipment and
extra fuel
ii)
“Squeezing”
the fuselage to closely wrap around the F414 which is 103 mm smaller in
diameter. This will reduce the transonic cross section and help improve drag, transonic
acceleration and energy related performance as also further weight reductions
but reduce the radius of action compared to i) above.
5.
Deletion of VG
and lowering of wing datum
i) As already indicated the VG feature is no longer strictly
necessary and the wing will be replaced by a wing of similar area and aerofoil
section but with the sweep fixed at approximately 45 degrees. The LE flaps will
be improved and made full span the technology developed for the LCA. A study
will also be made to compare the performance with the wing using the Sukhoi Su
7 aerofoil section which was noted for its excellent handling in combat speeds.
ii) If roll coupling problems have been
reported it may be possible to improve this by lowering the wing datum by the 53
mm vis a vis the centre line of the fuselage. Coupled with the lighter engine
the handling of the aircraft in rolling will improve.
The elimination of the extreme sweep of
72 degrees will give a bonus in that the Aerodynamic centre (AC) will shift
back much less. Consequent to the reduction in the AC movement the “tail
volume” will be reduced Hence the rear fuselage aft of the Cg will be reduced
in length by about 1 metre saving weight and drag.
6.
Elimination of
folding underfin
It is expected that the fin and the tail plane will
be reduced in size and it is quite possible that the folding under fin can be replaced
by a smaller fixed under fin/eliminated with saving in weight and drag.
7.
Relocation of
pylons for better optimization
To avoid the usage of variable sweep pylons as in
the American F 111A the Russians elected to put all the pylons in the wing
glove. This was sub optimal as the forward cg meant a larger than necessary
tail empennage as well as a heavier nose under carriage. With a fixed sweep
wing it will be possible to relocate some of the pylons out on the wing thus
relieving wing bending moments as well as allowing the missile sensors a
greater field of view. The weight of the nose undercarriage can be reduced.
8.
Smaller engine
inlets
The smaller mass flow of the GE engine 86 kg/sec vs
105 kg/sec means that the intakes will be smaller. This will result in weight
and transonic drag reduction whilst the greater L/D ratio of the intake duct
means that better “surge resistance” can be expected during gun firing.
Alternately if the fuselage cross section is kept
same as the present (p.6 pt.4) an additional 550 lits of fuel can be stored.
9.
Deletion of JATO Pylons
The MiG 23/27 was equipped with JATO pylons to meet
rough field operations. If these are not a part of the doctrine these pylons
will be eliminated saving weight and drag.
10. Artificial Intelligence
AI will be introduced into the aircraft to improve
serviceability as well as give a pilot reminder and warning aural messages.
Depending on the advantages of each incremental surgery the changes have to be
menu-ed against time and organized into a minimum list and subsequent changes
can be introduced as per production block. The LCA Mk1 software already
developed can be incorporated.
Weight Savings
The
MiG 23 aircraft was designed using the technology of 60 years go. Improvements
in technology since then has resulted a possibility of considerable savings
which could radicalize the concept of the aircraft.
Direct savings.
Feature changed Weight Weight
saved
Elimination of the VG mechanism 400
kgs.
(Estimated from Soviet sources)
Replacement of engine R29B by F 414
Weight of Tumanskii R29B 1830kgs
Weight of GE 414 1130
kgs 700kgs
Replacement of Radar
Weight of
Saphir 23 385
kgs
Weight of Elta 1M2032 100kgs 285 kgs
Total direct
weight saved 1380
kgs
The direct savings will lead to further indirect
savings due to aerodynamic and structural reasons. These are:
1.
Reduction
in fuselage lengths approx 1mts as AC
movement is reduced 100kgs
2.
Deletion
of folding ventral fin 85
kilos
3.
Reduction
due to ducting cabling wiring pipeline etc 100
kilos
due
to 1 above
4.
Reduction
in tailplane area due to lower a.c. shift 50
kilos.
5.
Due
to replacement of Soviet era connectors 60
kilos
6.
Due
to lighter wheel and brakes of modern technology 75 kilos.
7.
Due
to better location of pylons and deletion of RATO pylons 40 kilos
8.
Weight
improvement to the undercarriage 40
kilos
There
will be a significant saving in changing from Soviet era connectors and 28v
electrical systems to modern Western equipment and 115 v. constant frequency
systems as no doubt the Air Force is well experienced in.
Generally
a two ton (2000kgs) weight saving can be expected at this stage of estimation.
The prototype
aircraft can expect to be around 7500 kilos basic empty weight without using composites which can be
introduced only after the design is proven. Using
composites on the wing skins alone can save around 350 kilos above the given
figures and they should be introduced in the later blocks.
The Limits of
the study
To
serve its purpose such a study should be
severely limited and focussed scope to be achieved in a strictly defined time. The
study is a “what if we do this – what will we get “ confirmation of the above
idea and should not take more than 2 to 4 crores per study though no doubt people
can find means to overshoot the budget.
The
study should explore:
i)
Does
the MiG 23/27/F414 hybrid meet the MK2 specifications without any concessions?
ii)
The
extent of “stretch ability” of the design over the next two decades to
accommodate future growth. The layout will score heavily in this.
iii)
What
and where the information resources are available should the project go up to
the next stage.
iv)
The
cost estimates and timescales for an FSED and for the next step i.e. detail
design and mock up.
Scope of the
work
i)
Preparation of three project studies using the F414/
Eurojet/M88 and Russian engines and along with matching accessories. This is to
avoid commercial pressures which will be inevitable if the project is
attractive.
ii)
Performance studies based on comparative CFD and
wind tunnels studies. The availability of the MiG 23/27 will be particularly
valuable in underwriting the data.
iii)
Identification of resources required to build mock
ups and or prototypes and their availability in India.
Other
Project studies
There should be the following other
project studies either jointly with the original licensor or independently.
These should cover:
i)
Jaguar “big wing” with the
Maritime fuselage which was an original BAe programme in the 1980s.
ii)
The
HF 24 powered by the Honeywell F 125.
The airframe’s potential is unarguable and its known quirks can be tamed by
modern technology.
iii)
The
MiG 21 UPG/LCA systems packaged in
to a modified air frame based on the
Gnat much as the Orpheus powered Gnat was evolved from the Viper powered
Midge of one third the power of the Orpheus. The peculiarities of Military
marketing are such that people will listen to a “Combat Hawk” proposal but not
consider a superior solution in the Gnat re- surgery.
It
appears that the HF 24 drawings and documents have been destroyed. This
requires an investigation but the
absence of drawings does not stop the HF 24 from being considered as a base
for initial project studies. Modern e-engineering techniques such as laser
scanning and spectrography can regenerate all the data on the platform and the
rest of the study is no more than an upgrades programme. What will be needed
will be a one or two airframes in a reasonable state of preservation. The
technical history of the programme can be recreated given our great oral
traditions as exemplified by the Canberra reintroduction.
Intellectual
property Rights
issues may rise but since structural surgery with new equipment and systems the
resulting aircraft is essentially new and so IPR problems can be tackled. In
any case the vendors would be tackled by the prospects having lucrative markets
for the supply of the accessories and can be handled at the Government to
Government levels.
Estimated
Manpower
A
total of 10,000 to 15,000 man hours need to be budgeted for. Tentaitively the
need is for 6 engineers preferably with about ten years MiG 27 experience and
about 6 CAD/CAE engineers capable of working under guidance on modern CAE
software. Another two documentation staff would be indicated ,i.e. 15 engineers
working for six months.
Work location
Modern
communications makes the workplace location less important. Closeness to the customer to understand his
needs is the first requirement. The ideal at this (preliminary) stage would
be Air HQ as a project cell or IIT New Delhi. Admittedly IIT New Delhi does not
have an Aeronautical Department but it is overruled by the fact that the
project cell can be in almost daily interaction with the Customer and the
industrial back ground of NDLI can allow for small mock ups etc to be quickly
fabricated.
The
other location could be BRD 11 Nashik which would have the base aircraft at
hand. In the case of the Delhi location one CAT C sample of the airframe and as
much documentation as available will have to be located at the campus.
Conclusions
It
is common sense and standard practice that when unproven technological advances
are incorporated into a design to have not one but several plan Bs. These plan
Bs are carefully calibrated in terms of risks against an abscissa of time. Such
efforts are continued until the main project is reliably out of the woods.
Failure to do so has created the crisis.
Contrary
to the views broadcast bt the import lobbies the keeping of multiple projects
is not expensive. It would have cost us only 50 or 60 crores i.e. 10% of the
LCA budget of that time over perhaps six years to have funded any of the HF 24
based derivatives in 1983. The annual additional expenditure would have been in
the region of perhaps ten crores. The impact of having a HF 73/HF25 prototype
around 1989 does not need elaboration.
We
cannot correct the past. The present has to be seized. The LCA Mk2 as much as
the LCA mk.1A and the.AMCA must have at least shadow competitors at this
nascent stage.
Prodyut
Kumar Das
Engineer
.Professor (retd)
Kolkata
April 20 -2019
Sl.no.
|
Parameter
|
MiG 23/27
|
Redux
|
1.
|
Length
|
16.84
|
15.04
|
2
|
Span
|
13.995/7.779
|
10
|
3.
|
Height
|
5.145
|
5.145
|
4.
|
Wing
Area
|
37.27/34.16
|
34
|
3.
|
Empty
Weight
|
9595
kgs.
|
7500-7000
kgs.
|
4.
|
Clean
TO with 2 CCMs.
|
14,625
kgs.
|
12,625
kgs.
|
5.
|
MTO
|
18,570
kgs.
|
16,975.kgs.
|
6.
|
Internal
Fuel
|
4670kgs.
|
4670kgs.
|
7.
|
Fuel
Fraction
|
0.5586
|
0.80/0.5586
|
8.
|
Engine
Thrust
|
83.6/127
kN
|
57.8/98
kN
|
9.
|
Wing
Loading ( clean Combat)
|
430
kg/sq.mts.
|
371
kg./sq.mts.
|
10.
|
Power
Loading ( clean combat)
|
0.886
|
0.89
|
11.
|
Fixed
Weapon
|
6x30
GSh.
|
6x30GSh.
|
The three view drawing sshowing the MiG 27 fuselage with the LCA wing panels and one with a MiG 27 based wing at fixed sweep will be published in due course.
I agree Tejas should have been a competitive tender with HAL/ADA making one proposal and possibly the private sector making another proposal. The two proposals could've given birth to two prototypes to allow for a flyoff competition similar to how the US military runs their aviation procurement programs.At the moment HAL/ADA have a monopoly and as with any monopoly they are inefficient. But, I think suggesting the Mig-23/27 as the basis of a Modern fighter is a bit far fetched, the Mig-23 and 27 were quite capable fighters in their time but there airframes are part of a bygone era. Just look at the swing wing capability which doesn't have space on a modern battlefield, it is just dead weight and extra maintenance/lifetime costs. Instead of the Mig-23/27 a mirage 2000 would be a more accomodating basis for a teas Mk2 basis. In either case both the Russians nor the French would be very happy with Indian engineers reverse engineering their products. I would've thought a better solution would've been to buy the design work for a fighter like the IAI LAVI from the Israelis and bring it up to modern standards, essentially what the chineese did with the Chengdu J-10.
ReplyDeleteDear Sanku
DeleteI would think that both ( the MiG 27/IAI Lavi) are bad suggestions. But desperate situations call for do desperate measures. We need CERTAINITY in our defence programmes but that is not happening- almost as if by plan!
Have you thought what is obsolete in the MiG 27 fuselage? It is perfect for the LCA specns.I have NOT asked for the VG to be retained! You will save about 500 kilos and then some. If you read carefully -which you have NOT- you will see that I am calling for a MiG 27 fuselage -shortened somewhat- VG deleted and equipped with either the LCA wing or a fixed area fixed ( Non VG) mod of the MiG 27 fuselage but with teh MiG 27 empennage.. According to my study this will solve many of theconcessions being asked for.I amasking for a "What if we do this study". It wont cost the sky if you know what you are doing. We should not ignore the study.