The Tejas costs Prof.
Prodyut Das
Introduction
The
Tejas is without doubt the longest running project in Aviation History. Any
criticism of the project is countered not by debate but by "flank attacks" the following being typical examples:
i)
The
critic has ulterior motives and likely to be in the pay of the import lobby. Going by the fact that it is ADA's failure that has helped the import lobby- this is rich.
ii)
The
aircraft –an wonder of aviation design “just round the corner” wrt to
readiness for production. It has been that way for the last two decades.
iii)
It
is the cheapest programme in the world and ADA has done a marvelous job on
such a small budget. American programmes are hugely expensive running into billions.
In
fact the last has been repeated so loudly and so long that most critics tended to accept that as de facto. Recently I did some
calculations and it appears that the Tejas Mk1 development costs are roughly
33% MORE than the development cost of the F16. This is shocking because
development costs in India should be 1/3rd to 1/5th the
cost in America.
Analysis
of costs is important because of the general threat environment, the parlous
state of the IAF and the need to beef up R&D strength and funding. However without increasing the efficiency of the organization the scarce resources will
be wasted.
Methodology of the
analysis
Given
the seriousness of the topic and in the
interest of a meaningful debate I am detailing my procedure so that
commentators can do their homework before commenting.
1.
The
development cost of the Tejas programme was taken from the DRDO/INSDOC sources
(Ref1)
2.
The
cost of the American F 16 programme was taken from American official sources.( Ref2)
3.
The
costs were compared by the following steps:
i) The DRDO figure of Tejas development cost is Rs.14,192 crores. This is the arithmetic sum and misleads. The
Tejas programme had to be re-financed every ten years or so. Since the
programme ran from 1983 to 2011 to achieve IOC 1 and because inflation is
significant over long periods the amount of money at various times had to be
brought to a common value –present day value -PDV- was used. This was to get a
feel of the value of what we spent actually.
ii)
To arrive at the PDV the official inflation rate of the GOI for that year was used
iii)
The
American programme to IOC was much tighter- 7 yrs. The highest figure– 1977
dollars- was used as the development cost.
iv)
Comparisons
could be done by factoring in PPP but there was a conflict of what DRDO
official state in Ref .1 i.e. Re1=$1 which is rubbish and the most likely
value $1= Re.10. To avoid any controversy I therefore converted the sum
sanctioned into weight of gold purchasable by that sum at the time of
sanctioning.
The
result shows that the F 16 was developed by spending the equivalent of 208 tons
of gold whilst we spent the equivalent of 275 tons of gold to reach a very patchy IOC 1. This is against the figure of 36 to 46 tons only that we should have used. The
American programme was about 33% cheaper and at IOC the F 16 could fire its guns in anger something even the FOC Tejas cannot do even today!
Any claim that ADA programme is much cheaper than foreign programmes is
unsustainable.
A discussion of the
results
1.
Generally
product development in India should be 1/3rd to 1/5th the
cost of developing the same product in the West. This is because the manpower costs in India are significantly cheaper in India. Compare HAL and Boeing salaries. It is borne out from personal experience in developing aerospace an defence products.
2.
In
Aeronautical Development where the cost of trained manpower is 70 to 90 % of
the total project costs cost India should actually have even higher a competitive advantage.
3. The original estimate of Rs 560 crores ( 26.7 tons of Gold )was probably done by Raj Mahindra and was quite realistic but would have
needed a supplement of another 2-300 crores (in 1986 money) i.e. 10-20 tons of gold i.e
total 36-46 tons of gold but 275 tons is clearly unexplainable.
4.
Misuse
of funds is a possibility. Indeed the case of a wooden wind tunnel model being
bought for a hundred time the price at which the Americans bought a similar
model has been mentioned; there is also
mention that Dr. V.S. Arunachalam was
accused by an MP for misuse of funds and threatened with dismissal.(Ref.1). The
CAG reports of that time (1980s-1990s) were unhappy with the keeping of
accounts.
5.
The
role of delay in pushing up costs is often not appreciated. As an example the
salary and perquisite cost along with the support costs i.e. the money needed
just to populate the ADA building would be a drain of 15-18 crores a month i.e. A five year period
would see through a 1000 crores. ADA does project studies in 7-10 years, a
delay of five years between roll out and first flight and two years to go from 22
to 24 alpha. At that pace no budget will be enough.
6. The harmful effect of serious cost over runs- the Tejas should have been done till IOC at Rs. 14-15,000 crores PDV instead of Rs. 55, 000 + crores PDV is that it starved other needy projects. If this is typical of other DRDO projects then India will never have enough funds available for all its defense needs because the systems is too inefficient.
Table 1.
1 |
2 |
3 |
4 |
5 |
6 |
7 |
8 |
Sl.No |
Item |
Amount |
Yr |
Inflation |
PDV2022rs.Crores |
Gold.
Rs/10gms.24 k |
Gold
wt. in Tons |
1 |
1st
Fund |
560 |
1986 |
12.102x |
6777 |
2140 |
26.7 |
2 |
TDF |
1628 |
1993 |
6.433x |
10,477 |
4140 |
39.3 |
3 |
FSED |
7428+2573 |
2004 |
3.54 |
23,427+8115 |
5850 |
126.97+45.53 |
4 |
NLCA1 |
2103 |
2003 |
3.57 |
7507 |
5650 |
37.22 |
|
Totals |
14,192crs. |
|
|
55,428
crs. |
|
275.21 |
The American Budget
The
American F 16 had a swifter genesis and development. Sanctioned somewhere in
1969-70 it was ready with IOC in 1976 at a cost of $ 891 million. Given that
and the much lower rate of inflation in America at that time 1.5-2% the
inflation has not been factored in but the final higher value in 1977 dollars-
the Americans are budget conscious-has been taken. The value of gold was $133.7
/troy ounces. This gave a weight of gold
as 208.19 tons was spent to develop the F 16 to IOC which in teh US means ready for combat.
Conclusions
1.The impression that in ADA we have a R&D organization which is a bit slow but we are getting
the development at a low cost is not borne out by the above. This may not be
true of all DRDO organizations but certainly ADA needs a revamp and broad basing of
its management or it will continue to fail and fail expensively.
2. By cornering a very large slice of the funds the Tejas project created a "drought" of funds and technical manpower for other projects . Well managed the alleged scarcity of funds should mitigate.
References
1. Radiance in the Indian Skies -The Tejas Saga-Air. Mshl. P Rajkumar and BS Srikanth DRDO Min. Def. India
2. 00100 - [A1051857 ]
Status of the F-16 Aircraft Program. PSAD-77-41; B-i63058. April 1, 1977. 21 pp. Report to the Congress; by Elmer E. Staats, Ccmptroller General.
Comments
Post a Comment