Save the IAF-Revive the Marut Prof. Prodyut Das
24/01/ 2025
There are now two distinct opinions about the Tejas
programme.
The first is that the Tejas is brilliant aeroplane “a
pearl” one worthy famously quoted about two decades ago (if nothing, shows
how long we have waited for irresponsible promises to be fulfilled!), whose
success now the perfidious Americans are trying to sabotage by delaying the
supplies of engine, The second view is that the Mk1is a bit of a joke and all
subsequent proposals, Mk1A, Mk2 TEBDF etc are clumsy attempts as the inept
Design Agency stumbles from one half- baked solution to the next to correct the
blunders of the Mk1.
No matter whosoever is right, the IAF cannot even begin
to check the decline in its numbers, let alone rebuild its air strength. This
is because:
If the first view is right then the US will continue
playing games. Calling it “supply chain issues” won’t make the problem go away.
If it is engines now it will be the Composites next. It is worth recounting
what has happened before. The Viggen was offered for the NATO Starfighter
replacement competition along with the Mirage FIE, and the F16. The problem was
even though the Swedes had re-designed the civil JT8D engine- a larger
fan, improved combustors, a thrust reverser and the after burner they still had
no say over the engine. Note that the JT8D was a civil engine used on the B737
and being churned out like sausages. The point is if the Tejas is
a threat to US products it will be tripped up. Unfair? Well, even if we get
around to really making a wonderful aeroplane we won’t get to make the rules.
I have put “civil”
in italics to emphasize the need to think boldly and differently, starting from
fundamentals and not parrot the strategies of others. So, even if the Tejas is
good (which I most definitely do not think so) then we will be sanctioned and
if it is even half as bad as I expect well then, the Tejas has scored a goal
for the Import Lobby. As I said no aircraft either way.
Suppose we wanted a fighter that would, short of open
warfare, be reasonably free of sanctions then below is an assessment of the
workload.
The best engine option would have been the HTFE 25 but
somehow the same set of people who stopped the Kaveri engine programme in 2008
seems to have stopped this important programme also. Presuming that the HTFE 25
and it’s afterburner is has been halted the next option would be revive the Orpheus B.Or.12
concept.
A tabulation of the work load remaining in developing
a sanctions free fighter.
|
Aircraft
Project |
Structural |
Systems |
Engine |
Testing |
Remarks |
1 |
Tejas
Mk1A/F404 |
Critical
Weight improvement required |
Presumed
OK |
Subject
to sanction |
Presumed
OK |
Poor
producibility High- Cost design. Near useless for combat |
2 |
Tejas
Mk1A /Kaveri |
Further
critical weight improvement |
As
above |
Engine
requires further development and a
further 15,000 hrs of testing |
As
above |
Better
but Kaveri design requires urgent “different Thinking” attention |
3 |
HF
42/Kaveri |
About
50% of the airframe aft of front fuselage to be designed |
Repackaging
of Tejas systems. Only “trimming” tests required |
Kaveri
remarks apply |
Further
validation required |
Cheaper and easier to build than Tejas |
4 |
HF
24/ Orpheus based engine |
No
change in any prime structure |
Tejas
systems with interfacing to be worked out |
Pl.
see note below |
Tested
airframe |
Sanctions
proof. Lowest cost. Cheaper and easier to build. |
Given the above situation i.e. that the “conventional
thinking” set of solutions is liable to sanctions and the sanctions free
solutions requires a start to be made, the surprise logical solution, is to
focus on the 4th option,
The 4th
option
The advantage of the fourth option- based on the HF 24
airframe and an engine based on the Orpheus and equaling the original B.Or.12- that
our development load will be the least:
On the airframe: Only installation and repacking of
systems. This task is made easy by the fact that the HF 24 has 40% more internal
volume and much more real estate externally than the Tejas. Much of the
certification testing has been already done and hence can be dispensed or
boldly proceeded with.
On the engine: To frugally infuse a 1952
technology engine with some, but not all of the 1980-1990s technology developed for the
Kaveri so that the Orpheus 21 kN thrust is raised to 30kN. and an AB to
increase the wet thrust of 43 kN. The Marut design does not need more. It will be more uncertain to develop the better Kaveri as compared to develop the simpler Orpheus. Pl. See
the note on Orpheus development at the end.
Operation
Salvage
The US, whose budget allocations we cite and envy so persistently,
would have closed down the Tejas programme long ago but we are Indians, The
first step would be to continue to try and salvage the Tejas programme. We cannot let defaulting organizations get off
the hook with bragging rights intact by stopping this programme.
1. Have
the Tejas design examined by a fresh set of people. No foreign consultants; they are not needed. As the HJT 36 has shown, it has been 11 years since
foreigners were consulted and we still don’t have the product.
2. Crack
the whip. Order the Tejas Mk1 empty weight to be reduced to below 5800
kgs i.e. the airframe weight is to be less than 1900 kgs and the U/c to be no more
than 90% of the MiG 21bis undercarriage.
3. “Now
it is ALL HAL’s problem” speaks of lack of professionalism, irresponsibility
and a tacit admission that solving the created problems is beyond the capabilities
of ADA. All agencies have to be equally responsible and have to work together.
4. Give
option 4 to a funded (at the same rate as DRDO development projects) with a
Private sector Consortium working to re produce the Airframe and develop the
engine (henceforth referred to as Engine R 19)
Conventional thinking would balk at yet another
proposal but reality is that this proposal is most likely to succeed.
The Marut R 19 proposal is promising because the Tejas Mk1 is undevelopable
which is why it has taken 24 years after first flight and we are still
debugging it. The other possible conclusion would be that ADA is in someway either incompetent or unwilling to complete the job. The engine is trying to catch up with GE levels of performance.
Given these, the Super Marut project uses existing experience to the maximum
extent with careful usage of very discreet amounts of new technologies to give
the customer full satisfaction and be politically “sanction” proof.
Note on developing Engine R19.
Kurt Tank developed the HF 24 around the Orpheus B. Or. 12 which was expected to give a dry thrust of 30,3 kN and a wet thrust of 39kN. Note two B,Or, 12 Orpheus would have slightly higher thrust as a GE F 404. The Orpheus B.Or.12.had
developed its rated dry thrust of 30.3kN, passed it’s 150 hrs qualification
tests and by 1956, the un-reheated engine had flown in a F 86 Sabre test bed.
The after burning model developed 36 kN. It is to be noted that these thrust
figures were achieved using early 1950s technologies. We in India must surely
have crossed those levels handsomely bar engineering leadership which is
conspicuous by its absence in some of the labs. The Dhruv ALH with 300 plus
produced and with over 300,000 hours is proof that requisite Leadership was not
lacking but is being kept out. The Orpheus engine was developed, within a span of twelve months April
1952 to May 1953 using earlier Bristol Orion’s Compressor as a base.
Using similar development strategies, it should be possible to develop the R 19 relying heavily on the existing engines – Orpheus and Pegasus cores- to achieve what is needed in terms of above thrust- not the world best or any particular T/W ratio or s.f.c.- but adequate to do the job.
The major design constraints would be what is the TET we can achieve. The Orpheus TET was for max. continuous cruise was 927 deg. K and I presume we are at present entirely comfortable about achieving 1300-1350 deg. K. Any proven increase above that would be welcome. In terms of high temperature materials and production facilities no additions will be needed. We are basically gilding the lily of a 1950’s design.
Starter generator: The
existing bullet mounted starter generator is moved out by the overhung “zero
stage” to the top or bottom of the engine casing. This will result in an
increase of inlet area by almost 25% with consequent increase of mass flow, and
inlet pressure drop improving thrust.
Compressor: The
compressor is based on the Orpheus or Pegasus core compressor. In the case of
the Orpheus a “zero” stage is added giving a total of 8 stages, the Pegasus
core already having 8. The “zero stage” is overhung so that much of the
de-icing equipment can be done away reducing weight and bleed related losses. The
overhung zero stage will require relocation of the starter but as indicated above will increase
compressor face area by 29% with consequent possibility of increasing mass flow
and thus dry thrust.
Combustion Chamber (CC) ; Pressure
drop in CCs of this vintage were relatively high. It would nevertheless be wise
to retain the existing system initially making only such common- sense changes
as would be indicated by CFD studies. The Orpheus has a very simple but “bitty
detailed” combustion chamber but one which makes production rejections easier
to control. A parallel study could come later to have modern low loss annular
CCs will decrease the energy loss due to combustion chamber resistance/
Turbine Inlet Guide Vanes (IGV). The
existing IGVs are already air cooled but changes in material and internal
contours will be required.
Turbine blades. Given the
increase in TET it would be overloading the existing turbine resulting in
unreliability and a two- stage turbine with a relatively lightly loaded first
stage may be the trick given our anxiety about achievable TETs within
metallurgical constraints. The two stage turbine would also improve TBO and TTL.
Internal adjustable jet coneThe early German jets used a sliding “onion bulb” to coax the maximum performance from the BMW 003. That idea was used in the early ATARs but fell out of use with engine thrusts increasing rapidly. Pending development of a complex and heavy fully variable nozzle it would definitely be worthwhile to look at this simple solution for a simple low power jet like the R 19.
AFRC. For trials the present AFRCs are to be retained but if project appears promising work should start on a hybrid controller using at least electronic sensors for the usual control parameters.
A table of Comparisons Dimensions in MKS unless stated otherwise
Sl.No |
Component |
B. Or. Orpheus 3 |
R 19 |
Remarks |
1 |
Length |
1923 |
2023 |
Due to added
“zero” stage |
2 |
Dia inlet/Max |
649 |
649 |
25% more inlet area |
3 |
Dia Overall Max. |
822 |
822 |
|
4 |
Weight |
379 kg. |
480 kg |
Simple after burner |
5 |
T/W |
6:1 |
6.2:1 |
|
6 |
Compressor |
7 stage single spool |
8 stage single spool |
Based on Orpheus or Pegasus compressors |
7 |
Compression ratio |
4.4 :1 |
6:1 |
|
8 |
Turbine |
1 stage |
2 stage |
Improved TBO |
9 |
Turbine/ TET |
9270 K max. cont (3285) |
13500 K |
TET will be revised upwards with time if survey
warrants |
10 |
Thrust Dry/Wet |
22kN/na |
30.3 kN/40 kN |
|
11 |
AFRC |
Mechanical |
Hybrid/FADEC |
|
12 |
Power take- off |
4kW |
20kW |
|
Total test hours for all variants -about 5 - is 12,000 hrs on the bench and flight tests were 5600hrs
It is estimated that a Private sector consortium gathering a team of 50-60 people should be able to produce mass production worthy examples of the engine and a similar team the airframe in about two years and appropriate costs. The design team would do well to see if existing engines Orpheus or its components could be used to develop a few static non-flying test engines.
Project costs
Costs are highly subjective depending on the “indenting agency” of the funds and the degree of cost control. Our costs do not stand scrutiny and indeed on one very major project the accounts of the first ten years or so are reported to be missing.
An approximation of what it should cost is given by History itself. Bristol originally asked for GBP 1 million to do the engine development and later lowered it GBP 300,000 which is equal to INR 1.2 Crores to INR 36 lakhs @ INR1958 respectively. The amounts would represent about Rs. 120 crores to 36 crores in Rs@ 2025 values all inclusive. That would give a starting figure.
By the same token the HF 24 aircraft was developed for a cost of Rs14 crores which would be equal to Rs 1400 crores. These may seem incredible but are achievable with good teamwork and management. Most of our project costs- by my estimates much higher then US costs- are due to fundamental mistakes being made at the start of the design and then those mistake are inexpertly attempted to be corrected.
Involving the Private sector
One of the reasons one urges the handing over of some projects
to the private sector is that the programme leaders and their monitors are
people who have risen on their track record in achieving set targets. They pick
up extraordinarily fast and can get into the details.
They
also have continuity- the successful spend near 50 yrs. in the Company and the unsucessful are quietly weeded out.
Comments
Post a Comment